Build Time Planning

Edit on GitHub

Realistic time estimates per stage, what takes long, and how to parallelise ordering with building.

Build Time Planning

A realistic plan keeps the build fun instead of frustrating. The stages below assume a first build with modest soldering experience and no special tooling beyond an iron, solder and a multimeter.

Time per stage

StageFirst buildSecond build
Sourcing parts and waiting for delivery2-10 days (shipping dominates)Same
Bench setup and tool check30-60 min10 min
Power path (TP4056, divider, cell holder)45-90 min25 min
Display (OLED software SPI)30-60 min15 min
Radio (E22 module, VSPI)45-90 min25 min
Controls and LEDs30-60 min20 min
Audio path20-40 min15 min
GPS module20-40 min15 min
Enclosure and final fit1-3 h45-90 min
Bench test pass (all gates)1-2 h30-60 min

Total for a first build: roughly 6-10 hours of bench time spread over the days while parts arrive. A second build with parts on hand is 3-4 hours.

Where the time actually goes

  1. Waiting for parts dominates the calendar, not the bench. Order the long-lead items (E22 module, OLED, GPS from Asia) first, and bench items locally.
  2. The enclosure is the single longest bench stage. Print or prepare it while the board is being tested, not after.
  3. Debugging is the unpredictable cost. The quality gates exist to convert unpredictable debugging into a predictable five-minute check at each stage. See Build Quality Gates.

Parallelise ordering with building

  • Order 1: E22 module, OLED, GPS, ESP32 (longest lead times).
  • Order 2 (while order 1 ships): TP4056, cell holder, buttons, LEDs, passives, enclosure.
  • Bench starts the day order 1 arrives; by then order 2 is on the bench.

The BOM Builder tracks quantities and totals, and its phased purchase order is designed around exactly this ordering logic.

Planning for a field deployment

If the beacon is for a specific trip, add two safety buffers: